This guide shows how to install solar panels yourself, on a roof, on a ground mount, or on an RV or shed. Can you do it yourself? For off-grid and small systems, yes. You can plan the layout, mount the racking and panels, wire the array and connect the rest of the system with ordinary tools and care. A grid-tied system is different. Connecting to your home’s electrical panel and the utility grid usually needs a permit, an inspection, utility approval and a licensed electrician for the final connection.

The steps below follow the order of the job: preparation first, then planning the layout, choosing and installing the mounts, mounting the panels, wiring, connecting the system, and the inspection. Safety notes come at the steps where they apply. Electrical and building codes vary by location, so check your local requirements before you start.

Before you start

A little preparation saves most of the problems that come up later:

Step 1: Plan the layout

Mark out exactly where each panel will go before you drill any holes:

Step 2: Choose a mounting system

The mounting system decides how the panels attach to your roof or the ground, and it’s where solar panel mounting brackets come in:

Mount type How it attaches Best for Things to watch
Roof rails with flashed mounts Aluminum rails on L-feet or brackets, lagged into rafters through flashing Most pitched shingle roofs Every roof penetration must be flashed and sealed
Rail-less roof mounts Each panel clamps directly to individual flashed mounts Pitched roofs, with fewer parts to lift Panel layout must line up with rafters
Ground mounts Steel or aluminum frame on concrete footings or ground screws Open land, no roof work, easy cleaning Needs space, and a buried cable run to the house
Pole mounts One or more panels on a single post, often adjustable Small arrays, deep snow areas Wind loads on the post and footing
RV, shed and flat-roof brackets Z-brackets, tilt brackets or ballasted frames Vans, RVs, sheds, flat roofs Sealing on RVs; weight and drainage on flat roofs

Buy racking from one manufacturer as a complete system, including its rails, clamps, flashing and grounding parts. Mixing brands can void the product’s certification and make the system harder to get through inspection.

Step 3: Install the racking

The racking holds the array through decades of wind and snow, so take your time:

  1. Set your fall protection first. Install the roof anchor according to its instructions and clip in before working near an edge. Extend the ladder about 3 feet (1 m) above the roof edge, secure it, and keep three points of contact while climbing. Don’t work on a wet, icy or windy roof.
  2. Drill into the rafter centerlines. Drill pilot holes at the marks, checking that you hit solid wood. A hole that misses the rafter has to be sealed and moved.
  3. Flash every penetration. Slide each flashing under the shingle course above, as the racking manual shows, so water runs over it. Use the specified sealant in the pilot hole and under the mount.
  4. Fix the mounts. Drive the lag bolts or structural screws to the depth the manual specifies, without over-tightening and crushing the roof deck.
  5. Attach and level the rails. Bolt the rails to the mounts, line them up with a string line, and adjust them to sit level and parallel. Use the manufacturer’s splices to join rail sections.
  6. Torque everything to spec. Tighten each bolt to the torque in the manual, using a torque wrench.

For a ground mount, set the footings or ground screws to the depth and spacing in the manual. Let concrete cure fully before you load the frame.

Step 4: Mount the panels

  1. Plan the lift. Panels are awkward and fragile. On a roof, have a helper hand them up, or use a ladder lift. Never carry a panel up a ladder alone.
  2. Set the first panel with end clamps. Place it on the rails, inside the clamping zones marked in the panel’s manual, and fix the outer edge with end clamps.
  3. Add the next panels with mid clamps. Each mid clamp holds the edges of two neighboring panels. Keep the gaps even and the rows straight.
  4. Torque the clamps to the racking manufacturer’s spec. Loose clamps can let panels shift or lift in high wind, and overtightened clamps can crack the glass.
  5. Bond and ground the array. The panel frames and rails must be bonded together and connected to ground. Many racking systems do this with bonding clamps or washers that bite through the anodized coating, plus a grounding lug on each rail. Follow the racking manual, since this is part of what the inspector checks.

Keep the panels covered, or their leads unplugged, while you work. Panels produce voltage whenever light hits them.

Step 5: Wire the array

Connect the panels into strings according to your design:

Our guide to wiring solar panels in series vs parallel covers each layout, and how to check its voltage against your charge controller on the coldest day of the year.

Step 6: Connect to the controller, batteries and inverter

With the array wired and its disconnect switched off, connect the rest of the system in this order:

  1. Mount the equipment. Fix the charge controller, inverter and disconnects to a wall or board near the batteries, in a dry, ventilated space, with the clearances their manuals require.
  2. Connect the charge controller to the batteries first. Fit a fuse or breaker on the positive cable close to the battery, then connect the controller and check that it recognizes the battery voltage. Our solar charge controller guide explains the settings to enter for your battery type.
  3. Connect the panels to the charge controller. Run the array cable to the controller’s PV input, check polarity, then close the DC disconnect.
  4. Connect the inverter to the batteries. Use the cable size and fuse the inverter manual specifies, and keep the cables short. Our guide to sizing an off-grid inverter covers fusing and grounding the inverter.
  5. Test before you load it. Switch on the inverter, check its output, then add loads one at a time.

To disconnect for maintenance, work in reverse: open the panel disconnect first and disconnect the battery last.

Step 7: Inspection and turning it on

If your project needed a permit, book the inspection before you switch the system on for regular use. Inspectors typically check the roof attachments and flashing, the grounding and bonding, wire sizes, fusing, disconnects and labels. Leave everything accessible, and keep the manuals and datasheets on hand.

For a grid-tied system, passing inspection isn’t the last step. The utility must also approve the interconnection and give you permission to operate before you turn the system on. Switching on before then can break your agreement with the utility, and a system feeding the grid without approval is a hazard to line workers.

After you switch on, check the charge controller or inverter readings over the first few sunny days, to confirm the array produces about what you expected.

When to hire a pro

A DIY install is realistic for many people, but some parts of the job are better left to a professional:

If your installation will be your only source of power, our guide to sizing an off-grid solar system explains how to plan for winter and long cloudy spells.

Frequently asked questions

Can I install solar panels myself?

Yes, for most off-grid systems and for small systems on sheds, cabins and RVs. You’ll need basic tools, careful planning, and fall protection for roof work. For grid-tied home systems, you can usually do the mounting and much of the wiring, but the connection to your electrical panel and the grid normally needs a permit, an inspection, utility approval and a licensed electrician.

How long does it take to install solar panels?

A small off-grid system on a shed or RV often takes a weekend. A DIY roof installation on a home usually takes several days of work, spread over more time for permits, the inspection and, for a grid-tied system, utility approval, which can take weeks.

Do I need a permit to install solar panels?

Usually, for any system on a home’s roof or connected to its wiring, and often for ground mounts too. Requirements for small off-grid systems vary more. Check with your local building department before you buy parts.

Can I put solar panels on a shed or RV?

Yes. Sheds and RVs are some of the easiest places to start. On a shed, check that the roof structure can carry the panels and racking. On an RV, use brackets designed for vehicles, and seal every screw hole with a sealant suited to the roof material.